A514 Crescent Link dualling, Derry - phase 2

 

Status
Construction scheme (completed)
Where
To continue the piecemeal upgrade of the Crescent Link in Londonderry to a dual-carriageway and the addition of a roundabout.
Total Length
0.7km / 0.4 miles (about 1/3 of the remaining route)
Dates

Included in Regional Strategic Transport Network plan 2005

Previous 1km opened 1 March 2004

Work to begin 3 April 2006

Completion due late July 2006

Most work on ground ceased mid September 2006

Officially opened 6 Nov 2006 (3 months behind schedule)

Cost

£1.0m (funded by private developers)

Photos
See below
See Also

General area map

A514 Crescent Link on this site - page about the complete road

A514 dualling phase 1 on this site

A514 dualling phase 3 on this site

A515 Foyle Bridge on this site

The A514 Crescent Link connects the A515 Foyle Bridge (and hence the northern half of the city side of Derry) to the main A6 road towards Belfast at Lisnagelvin. 1km of the route at the Foyle Bridge end has already been converted to dual-carriageway by the private developers of the Crescent Link Retail Park who also installed a new roundabout part way along the road. The £800k cost of that scheme was met by the developer.

Plans were announced early in 2006 to proceed with dualling a further 700 metre stretch and add a roundabout at the Kilfennan Link Road. The cost of this scheme will be met entirely by a private developer who is developing lands in the area. The second lane will be constructed off-line, ie beside the current road, so disruption should not be serious. The scheme also includes resurfacing the existing carriageway on this stretch. Unlike phase 1, phase 2 includes a central crash barrier.

See the "new and future road schemes" section for any progress on phase 3.

With thanks to Diarmaid Elder for advance notice of this scheme.

Photos

The completed Crescent Link phase 2 seen looking north approaching Crescent Link Retail Park on 16 Sep 2006 complete with its safety barrier – a first for the A514. [Photo by Diarmaid Elder]

Looking south along phase 2 of the Crescent Link dualling scheme in late August 2006, with work close to completion although apparently behind schedule. [Photo by Diarmaid Elder]

Work proceeding on the Crescent Link, seen here in late April 2006. The new carriageway is being constructed completely off-line, as seen in this view looking south. [Photo by Paul Gaskell]