A2 Caw Roundabout Upgrade, Derry 

 

Status
Construction scheme (current)
Where
To upgrade the existing Caw Roundabout by the addition of traffic signals, spiral lane markings and a left-turn jet lane for movements from the A2 from Limavady onto the A514 Crescent Link.
Dates

2015 – DFI decline to fund the scheme at public expense
2016 – Proposed housing development at Ballyoan renews pressure for the scheme
2019 – Planning permission for housing granted, requiring Caw upgrade partly at developer's expense and partly at DFI expense. Did not proceed due to funding pressures.
2024 – Developer agrees to fund entire upgrade.

May 2026 – Permission to progreed with upgrade granted
July 2026 – Work begins

Cost
£? (developer funded)
See Also

General area map - Google Maps

Click here to jump straight down to updates for this scheme.

Caw Roundabout is located on the A2 Clooney Road on the eastern outskirts of Londonderry, close to the southern end of the Foyle Bridge. It is a busy junction where the A2 meets the A6 road towards Dungiven and Belfast, as well as local roads serving the Waterside area. The roundabout has been the subject of concerns about congestion and safety for many years, particularly for traffic trying to enter from Waterfoot Park. In 2022 PSNI statistics showed it to have the highest accident rate of any junction in Northern Ireland. Calls for improvements date back to at least 2015, but the Department for Infrastructure did not initially consider an upgrade necessary.

The construction of a large housing development at Ballyoan (Rosses Gate), near Gransha, brought the issue back into focus. Planning permission granted in 2019 included a requirement to upgrade Caw Roundabout to accommodate the additional traffic generated by the new homes. The scheme will see traffic lights installed on the roundabout, along with additional lanes and changes to the road layout to increase capacity and improve safety. The works are being funded by the housing developer, South Bank Square, rather than directly by the Department for Infrastructure.

Despite the planning approval, the scheme was delayed for several years, partly because of its relationship with the proposed A6 Caw–Drumahoe dualling scheme and later by the need to agree the detailed design. Approval was finally given in May 2026, with work expected to begin shortly afterwards and be completed by the end of that year.

The diagram below shows the proposed upgrade.

Diagram shows spiral lane markings
                            around the roundabout with a new jet lane
                            going from top left to top right.
Diagram of the proposed arrangement (click to enlarge). North is to the left so the A515 Madam's Bank Road (Foyle Bridge) is to the lower left, the A2 from Granhsa/Limavady to the upper left, the A514 Crescent Link to the upper right, and the A2 Clooney Road into the city on the lower right. [Developer map]

Progress

16 Nov 2026: Work got underway at the end of June/early July, but I have only just added it to the site because there were so many updates to other schemes! The main construction work is the new jet lane from A2 -> Crescent Link. Work has also been taking place during October and November, including overnight closures between 7 pm and 6 am for civil engineering and resurfacing works. Presumably the whole roundabout is to be resurfaced before the spiral markings are added. DFI's traffic camera on 7 November was pointed towards the jet lane (see photo below) so you can get a good idea of progress. The kerbing seems to be in place. It is not clear when the works are due to be completed, but completion before Christmas is at least plausible.

High view along Crescent Link with
                              kerbing for jet lane visible on left, but
                              not yet surfaced.
DFI traffic camera view looking along Crescent Link with the new jet lane takijng shape on the left.